Querétaro: load, generation, grid
Peak balance, 2030 scenario
Grid demand (peak)— MW
Indicative supply— MW
Scenario
Data center connection mode
Data center load1,120 MW
Nearshoring industrial growth250 MW
Illustrative scenario input: new industrial load the state wants to attract by 2030, above organic baseline growth. The data center competes with it for supply and grid.
Policy levers
Peak-shave assumption
How much demand response and collocated storage shave the data center's grid peak. Illustrative planning assumptions, not measured: conservative 10/10, base 15/15, aggressive 20/25 percent (flexibility / storage).
○Live verdict · screening
—
—
Peak balance
—
grid demand − supply
Industry headroom (screening)
—
left for industry after DC
Clean build
—
to serve the DC energy load